IT-Tests.com has special training tools for IBM certification C2180-188 exam, which can make you do not need to spend a lot of time and money but can get a lot of knowledge of IT technology to enhance your skills in a short time. And soon you will be able to prove your expertise knowledge and technology in IT industry. IT-Tests's training courses for IBM certification C2180-188 exam is developed by the study of IT-Tests.com experts team to use their knowledge and experience.
Perhaps you have also seen the related training tools about IBM certification C2180-188 exam on other websites, but our IT-Tests.com has a pivotal position in the field of IT certification exam. IT-Tests.com research materials can 100% guarantee you to pass the exam. With IT-Tests.com your career will change and you can promote yourself successfully in the IT area. When you select IT-Tests.com you'll really know that you are ready to pass IBM certification C2180-188 exam. We not only can help you pass the exam successfully, but also will provide you with a year of free service.
Exam Code: C2180-188
Exam Name: IBM (IBM WebSphere Lombardi Edition V7.2, BPM Program Management )
Free One year updates to match real exam scenarios, 100% pass and refund Warranty.
Total Q&A: 38 Questions and Answers
Last Update: 2014-04-24
IT-Tests.com's IBM C2180-188 exam training materials is virtually risk-free for you at the time of purchase. Before you buy, you can enter IT-Tests.com website to download the free part of the exam questions and answers as a trial. So you can see the quality of the exam materials and we IT-Tests.comis friendly web interface. We also offer a year of free updates. If you do not pass the exam, we will refund the full cost to you. We absolutely protect the interests of consumers. Training materials provided by IT-Tests.com are very practical, and they are absolutely right for you. We can make you have a financial windfall.
Since IBM C2180-188 certification is so popular and our IT-Tests.com can not only do our best to help you pass the exam, but also will provide you with one year free update service, so to choose IT-Tests.com to help you achieve your dream. For tomorrow's success, is right to choose IT-Tests. Selecting IT-Tests, you will be an IT talent.
C2180-188 (IBM WebSphere Lombardi Edition V7.2, BPM Program Management ) Free Demo Download: http://www.it-tests.com/C2180-188.html
NO.1 The BPM program manager and process owner for a new hire onboarding process
project need to
ensure that the solution developed by the team will be accepted and adopted by the target
users. To
facilitate this, they decide to:
A. plan additional playbacks for user screens.
B. agree with users to postpone the release until every feature is correct.
C. involve champion SMEs in the discovery and implementation including playbacks.
D. insist on documentation of all user requirements before having the development team
begin work.
Answer: C
IBM C2180-188 demo C2180-188 C2180-188 exam dumps
NO.2 It is discovered while running Playback 0 that an important but not strictly necessary
sub-process was
missed in the analysis. How should the program manager recommend handling the missed
sub-process?
A. Redo Playback 0 and include the sub process.
B. Note the sub-process as a user story and save it for the next release.
C. Include the sub-process in Playback 1 without validating with the process owner.
D. Schedule a special iteration and playback to address the sub-process after Playback 3.
Answer: B
IBM exam simulations C2180-188 C2180-188
NO.3 The BPM Program Manager, Process Owner, and Lead Developer are collaborating to
define the theme
and assign user stories for the next iteration. The team is planning the 7th of 15 iterations in
the Release
Plan for Release One. The Program Manager displays a Team Velocity chart showing that
the
Development team has shown significant growth in story points accepted from iterations 1 to
4 and has
been leveling off to roughly 200 story points in iterations 5 and 6.
Given there are 9 iterations remaining in the release plan, the Process Owner immediately
recognizes
there is room for roughly 1800 story points in the remaining time for Release One. However,
the backlog
contains 2400 story points marked as "high" priority and another 1200 story points marked as
"medium"
priority. The Process Owner asks to reduce the points assessed to the high priority user
stories to bring
the total points down to roughly 1800 so as to make them fit in the remaining time. The
Program Manager
agrees.
What is wrong with this scenario.?
A. This is a conversation for a Release Planning meeting and not during Iteration Planning.
B. Team Velocity is fixed and changing the method of estimating story points mid-way
through a release
will not increase the scope of work that can be completed.
C. Process Owner forgot to include a risk factor of 1.4 that should be applied to 1800
resulting in roughly
2500 story points (1.4 x 1800 = 2520) remaining in the Release. No action should be taken.
D. Both "high" and "medium" priority stories should be included in the Release Plan meaning
all user story
points should be reduced by 50% to get all high/medium priority stories to fit in 1800 points
remaining
(2400+1200 = 3600 : 3600/2 = 1800).
Answer: B
IBM C2180-188 C2180-188 C2180-188 certification
IT-Tests.com offer the latest C_TPLM30_65 Questions & Answers and high-quality 70-462 PDF Practice Test. Our HP2-B111 VCE testing engine and HP2-K35 study guide can help you pass the real exam. High-quality ST0-237 Real Exam Questions can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.
Article Link: http://www.it-tests.com/C2180-188.html
没有评论:
发表评论